Automatic floor mortar screeding robots are evaluated based on the quality of the bedding layer and the handover time to the tiling team, including edge and doorway finishing.
Table of Contents
When the tiling team discovers a ripple in the floor right in front of a doorway, a portion of the work must return to the screeding team. At that point, the number of square meters the machine has covered holds little significance for the apartment handover schedule. With an automatic floor mortar screeding robot, both teams should agree from the start on the test area, the floor inspection method, and the person responsible for verifying results.
Selecting the Correct Material Layer and Test Area
The Fangshi JP210C Automatic Floor Mortar Screeding Robot serves the mortar bedding layer prior to tiling. CIC states that the equipment uses laser reference for leveling, with a reference productivity of 100 m²/h. This task occurs at a different stage than leveling fresh concrete during floor pouring. Therefore, demo requests should clearly specify the intended material, mortar layer thickness, and the handover elevation for the tiling team.

A typical apartment may have large rooms with enough space for the machine, narrow corridors, transition points at doorways, and edges near walls. Choose a test plot that includes at least one representative transition point. If testing only in the middle of the room, the contractor will have data for when the machine operates smoothly but will lack the information needed to calculate the labor required to finish an entire unit.
How to Interpret the ±1 mm per 7 m Specification?
CIC specifies a reference accuracy of ±1 mm over a length of 7 m for the JP210C. When documenting the test plan, both the value and the reference length must be maintained. If a room is shorter than 7 m or the project documentation specifies a different measurement method, technicians from both sides need to agree on an applicable inspection test. Recording only the "1 mm" figure in the report will result in the loss of necessary information to interpret the results.
On the test plot drawing, mark the inspection points or lines before construction. After screeding, record the results at the agreed locations, accompanied by photos if permitted. If adjustments are required at thresholds, mark the scope of the adjustment and re-inspect according to project criteria. When receiving the floor, the tiling team will know which areas are qualified and which parts are still awaiting processing.
Calculating Productivity Based on Tiling Team Handover
It is necessary to separate the equipment's operating time from the total shift time. For example, the machine completes the middle strip of a room and then waits for mortar to be transported to the next room. During this interval, the operating team is still present, and the tiling team may not have received a completed area yet. The log should record the start of preparation, waiting time, edge finishing time, and the final area handed over.
Before scaling up to multiple floors, compare the test shift with a manual screeding shift on the same type of floor. If the difference mainly stems from the mortar supply line, adjust the feeding position and test again. If the running time is stable but the doorway areas require significant manual touch-ups, make this task a separate item in the crew's plan.
What Should Contractors Submit to CIC?
Initial documentation only requires a typical floor plan, doorway locations, mortar type, and handover requirements. If the subsequent step involves the TZ432B Automatic Tile Laying Robot, the tiling team should be invited to participate in selecting the test plot. Contractors can register for a screeding demo and clearly state the objectives they wish to verify, such as the handover time for a complete unit or the flatness at transition zones.